A Message from the Trustees of the Pearl River Library
Thanks to generous support by voters, a $14.3 million bond referendum to modernize and improve the library was approved in May 2023. As it is now almost two years later, the trustees and staff want to provide you with another update.
Previous progress reports may be found at:
pearlriverlibrary.org/the-library-renewal-project
You are always welcome to attend the monthly Board of Trustees meeting at the library and/or to address questions to the interim director, Ed Falcone at efalcone@pearlriverlibrary.org. We strive to be transparent about the project.
Project Updates
As a school district library, the State Education Department (SED) has oversight of our construction project. Detailed plans were submitted to it on June 5, 2024, and in January 2025, they issued the required permits.
In the meantime, the trustees grew concerned that inflation and the threat of tariffs on prices might lead to bids over the project’s budget (the bond, the library’s capital funds, plus state grants and financial support from your state legislators, Senator Bill Weber and Assemblyman John McGowan).
Given this, it was deemed prudent to develop a list of items that could be deducted from the bidding so that a second round could be avoided. That would lead to months of delay. These bid alternates require documents prepared by the architect and approval by the SED. We are awaiting these approvals, which will permit the issuance of bids.
It is anticipated that these will be advertised this spring. Following review, a construction firm will be awarded a contract. The library now believes that construction can commence around Labor Day and will require around 18 months for completion.
New Location
The library moved to the former Ringner’s furniture store in January. The structure, now owned by a commercial real estate firm, had been renovated and made ready for the library in November. Rental payments began then, so it was necessary to make the move, even though the Franklin Avenue building will sit vacant for six months.
While the library re-opened in its new quarters in late January, the custodial staff continues to be busy emptying the former space. Old carpeting, computers and electronics, worn-out furniture, etc., have been removed to make the building ready for renovations. Some of the delays described above were impossible to anticipate, even in hindsight.
As you may have seen in the recent Library newsletter, despite these changes and challenges, we are offering more than 250 individual programs this Spring and are coordinating with a number of local businesses and organizations so we can continue offering the diversity of services the community has come to expect from us.
We thank you for your patience and promise that the new library will be a crown jewel for the community for many years to come.